FPID: 442764-2,-3

Introduction

Suncoast Parkway 2 Phase 3 will be a four-lane (two lanes in each direction) toll facility that extends from CR 486 to US 19, approximately 10 miles. The project will include the following:

  • Completing a full interchange at CR 486 to accommodate northbound traffic movements.
  • New interchanges at CR 495 and US 19.
  • Two (2) Electronic Tolling Collection (ETC) locations.
  • Related drainage, lighting, highway signing, traffic signalization, guardrails, and sidewalks.
  • The continuation of the Suncoast Trail, part of Florida’s Statewide Greenways and Trails System.
  • Realignment of W. Dunnellon Road to allow for a new interchange at SR 589 and US19. Widening and reconstruction of CR 495 (N Citrus Ave) at the proposed interchange.

 

Project Area

Map of Suncoast Parkway 2 (SR 589) showing construction phases, completed sections, and toll information.

Environment

The proposed roadway is following the approved alignment that was developed during the Project Development and Environment (PD&E) Study completed in 1998. The PD&E Study considered several alignment alternatives for the proposed extension of Suncoast Parkway 2/SR 589. The chosen alignment was selected based on providing the most efficient corridor to minimize impacts to residential areas and environmentally protected lands and species.

The 1998 State Environmental Impact Report (SEIR) developed during this process was re-evaluated in 2010, 2017, and 2022 for other design phases. The Enterprise performed a re-evaluation for Phase 3A in August 2024 and will perform another re-evaluation as part of the Phase 3B design segment.

Innovation

Florida’s Turnpike Enterprise is at the forefront of planning for a safer, more efficient, and technologically advanced transportation system for the future. The Enterprise continually seeks opportunities to integrate emerging transportation technologies that can help reduce congestion, create mobility choices, minimize environmental impacts and improve safety. The Enterprise also recognizes that connected and automated vehicle (CAV) technologies hold unprecedented opportunities for enhancing mobility and increasing safety on our roadways.

If you have an idea for a technology or innovation that you would like to be considered as part of this study, please reach out to one of the contacts in the Stay Connected section below.

Schedule

Phase 3A project timeline: Design starts Q1 2023, public meeting Q1 2023, acquisition Q4 2023, construction Q3 2025.
Project schedule graphic for Phase 3B: design starts in Q1 2023, public meeting in Q1 2023, acquisition in Q2 2024, construction in Q2 2026.

Stay Connected

Project inquiries, comments, innovation/technology ideas, or requests to be added to the project mailing list, can be mailed or emailed to:

Anil Sharma, P.E.

Project Manager

Consultant to Florida’s Turnpike Enterprise

Media inquiries should be directed to the FDOT, Florida’s Turnpike Enterprise, Public Information Office using the contact information below:

Fiorella Teodista

Communications Outreach Coordinator 

Florida’s Turnpike Enterprise

If you choose to provide feedback on this site or in an email, such information is a public record under Florida’s Government in the Sunshine Laws and available for public inspection upon demand. Under Florida law, email addresses are public records. If you do not want your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in writing.

Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability, or family status.

If you need special accommodations under the Americans with Disabilities Act or require translation services (free of charge), please contact the Project Manager using the contact information listed on this page. If you are hearing or speech impaired, please contact the agency using the Florida Relay Service, 1 (800) 955-8771 (TDD) or 955-8770 (voice).

Comment Form