This project’s Public Hearing is anticipated to take place during the first quarter of 2023.
The design for the Turnpike Widening from Partin Settlement Road to Osceola Parkway (FPID Number 436194-1) is anticipated to be completed by the fourth quarter of 2023. Right of way acquisition will be completed by the first quarter of 2024, and construction is anticipated to begin in the second quarter of 2024.
For the Turnpike Widening from Neptune Road to Partin Settlement Road (FPID Number 436194-3), the design is anticipated to be completed by the fourth quarter of 2025. Right of way acquisition will be completed by the first quarter of 2026, and construction is anticipated to begin in the second quarter of 2026.
Finally, construction is anticipated to be completed by the second quarter of 2028 for the entire project from Neptune Road to Osceola Parkway.