Central Polk Parkway East/451419-3, 455878-1 and 455879-1

FPID: 451419-3, 455878-1 and 455879-1

Public meetings were held for this project in August 2026. The same information was presented at each public meeting, including the project alternatives for all three project segments. A recording of the virtual meeting along with detailed conceptual plans are available for review in the Exhibit Room or in the ‘Documents” section below.

Use the “Locate an Address” tool to view the footprint of the draft highway alignment and interchange configurations, in relation to an address.

Introduction

The Florida Department of Transportation (FDOT), Florida’s Turnpike Enterprise (Enterprise) is conducting three Project Development and Environment (PD&E) studies for Central Polk Parkway East from US 27 to north of US 17/92.

Collectively, the studies will evaluate alternatives for a new tolled, limited-access highway from US 27 to north of US 17/92. Access points will be evaluated at US 27, SR 17, Lake Hatchineha Road (County Road 542), Marion Road (County Road 544), Johnson Avenue (County Road 580), Adair Road and US 17/92.

The proposed Central Polk Parkway East project will provide a link to Interstate 4 and SR 429 (Western Beltway) through the future Poinciana Connector (SR 538).

Flowchart detailing project phases: 1. Planning, 2. Project Development and Environment (PD&E) Study, 3. Design, 4. Right of Way Acquisition, 5. Construction.

The PD&E study is the second phase of the FDOT project development process.

PROJECT BACKGROUND

Located in the geographic center of Florida and along Central Florida’s I-4 corridor, Polk County is one hour from both Tampa and Orlando, and close to Central Florida attractions, making it a hotspot for growth.

 

In fact, Polk County ranks as the fastest-growing county in Florida. Between 2020 and 2025, more than 121,000 people moved to Polk County, and based on the Bureau of Economic and Business Research projections, the county’s population is on track to grow by 64 percent by the year 2050. The proposed Central Polk Parkway East project is just one infrastructure improvement project planned to address existing and forecasted transportation capacity deficiencies.

 

The need for the Central Polk Parkway East project includes:

  • Accommodating Year 2055 transportation demand
  • Improving regional connectivity
  • Enhancing freight mobility and economic competitiveness
  • Enhancing safety and emergency evacuation

 

The No-Build (No Action) alternative will also be analyzed and compared against the Build alternatives during the PD&E study.

Project Area

The proposed projects are in northeast Polk County.  Study limits for project 451419-3 are from US 27 to north of Lake Mabel Loop Road. Limits for project 455878-1 are from north of Lake Mabel Loop Road to south of Johnson Avenue, and limits of project 455879-1 are from south of Johnson Avenue to north of US 17/92. The projects will then connect to project 451419-1, a recently approved PD&E study with limits from US 17/92 to the future Poinciana connector.

The proposed Central Polk Parkway East project will provide a direct link to Interstate 4 and SR 429 (Western Beltway) through the future Poinciana Connector (SR 538).

Map showing future road connectors in Davenport and surrounding areas, including Poinciana Parkway extensions and routes.

ENVIRONMENT

Potential impacts to the unique natural, social, cultural and physical environments and related avoidance, minimization and mitigation measures will be evaluated during the PD&E Study.

 

The environmental analysis will include a traffic noise analysis and an assessment of potential wildlife corridors. The results of these evaluations will be available for public review.

INNOVATION

The Enterprise is at the forefront of planning for a safer, more efficient, and technologically advanced transportation system for the future. The Enterprise continually seeks opportunities to integrate emerging transportation technologies that can help reduce congestion, create mobility choices, minimize environmental impacts, and improve safety. The Enterprise also recognizes that connected and automated vehicle (CAV) technologies hold unprecedented opportunities for enhancing mobility and increasing safety on our roadways.

Icon depicting a car with wireless signals emanating from it, representing connected or autonomous vehicle technology.

SCHEDULE

Timeline graphic showing project milestones: Begin study in April 2026, public meeting in August 2026, hearings in 2027, and completion later that year.

Note: This schedule is subject to change.

Stay Connected

Project inquiries, comments, innovation/technology ideas, or requests to be added to the project mailing list, can be mailed or emailed to:

JAZLYN GEORGES, PE

Project Manager
Consultant to Florida’s Turnpike Enterprise

RONALD KAREIVA, PE

Project Development Engineer
Florida’s Turnpike Enterprise

Media inquiries should be directed to the FDOT, Florida’s Turnpike Enterprise, Public Information Office using the contact information below:

If you choose to provide feedback on this site or in an email, such information is a public record under Florida’s Government in the Sunshine Laws and available for public inspection upon demand. Under Florida law, email addresses are public records. If you do not want your email address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by phone or in writing.

Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability, or family status.

If you need special accommodations under the Americans with Disabilities Act or require translation services (free of charge), please contact the Project Manager using the contact information listed on this page. If you are hearing or speech impaired, please contact the agency using the Florida Relay Service, 1 (800) 955-8771 (TDD) or 955-8770 (voice).

Contact Form